Hani Sewilam chaired a meeting to review progress on the Kitchener Drain project, where 11 of 20 operations are complete and two have been awarded.
- Sewilam directed that implementation be accelerated and that contracting and tendering of remaining operations stay on the project's timetable.
- The ministry has completed 11 of the project's 20 operations, including reinforcing drain and branch canal embankments and supplying water-flow measuring devices.
- Two operations have been awarded and are completing contracting: field-level irrigation across 700 feddans and new lifting and mixing stations at Samatay and Al-Hamoul.
- Four operations are being prepared for re-tender, including rehabilitating seven pump stations, dredging 46.7 kilometers of drains in Kafr El-Sheikh, and supplying water-quality monitoring devices.