Egypt's transport minister attends completion of third tunnel machine on Cairo Metro Line 4
· Updated
Coverage
6 reports · over 83 hours
Kamel El-Wazir watched the third boring machine finish its section between the Al-Ahram and Al-Masaha stations on the line's first phase.
- Transport Minister Kamel El-Wazir attended the exit of the third tunnel boring machine at Al-Masaha station on November 15.
- El-Wazir said Concord's machine finished boring from Hadayek Al-Ashgar to Al-Ahram and Hassan Allam's machine from Al-Ahram to Al-Masaha.
- El-Wazir said the Petrojet machine is due to finish before the end of November, with Orascom machines boring the remaining stretch from Al-Fustat to Al-Masaha.
- The first phase spans 19 km and 17 stations, 16 underground and one surface, running from west of the Ring Road to Al-Fustat.
- Tarek Goueily, head of the National Authority for Tunnels, said the fourth machine, operated by Petrojet, will finish its work between November 25 and 28.
- Goueily said repaving and rehabilitation of Al-Haram Street will begin immediately afterward to restore normal traffic for residents of Faisal and Haram districts.
- Goueily said the first 12 stations of Line 4's first phase are targeted to open in 2027.