Egypt's transport minister announces completion of Benha–Port Said signalling upgrade
Coverage
3 reports · over 2 hours
Kamel El-Wazir said Siemens Mobility completed the 214-kilometre signalling and communications overhaul and that the Port Said signal tower has entered service.
- El-Wazir said the project covered 21 main signal towers, 19 secondary towers, 82 level crossings and 518 switch motors.
- He said the new electronic EIS signalling system installed on the line holds the SIL4 international safety certificate.
- El-Wazir said signalling upgrades are 100% complete on the Cairo–Alexandria, Beni Suef–Asyut and Asyut–Nag Hammadi lines.
- He said work continues on the Cairo–Giza–Beni Suef and Nag Hammadi–Luxor lines and on the ETCS L1 automatic control system.