Egypt transport minister inspects 64 km Rubiki–Belbeis railway as first phase reaches 97.5%
Coverage
3 reports · over 1 hour
Egypt's transport minister Kamel El-Wazir inspected the 64-kilometre Rubiki–10th of Ramadan–Belbeis railway, part of the Sokhna–Alexandria logistics corridor.
- Phase one: Bridge and industrial works on the first phase, from Rubiki to the 10th of Ramadan dry port branch, reached 97.5 percent.
- Track: 2.6 kilometres of railway have been laid in the first phase, while bridge and industrial works in the second phase reached 30 percent.
- Stations: Six new passenger stations are planned, two of them — Industrial Zone 1 and Obour 1 — with transfer points to the Light Electric Rail.
- Instructions: El-Wazir directed accelerated work and adherence to the timetable to complete first-phase track linking the 10th of Ramadan dry port to Sokhna port.